Echo Canyon Road - NPS road crew used a dozer to do the first pass for repairs. We still need to re-establish the permitted roadside campsites and run a grader down the road before opening. Likely to open by late November.
Hole in the Wall Road - NPS road crew used a dozer to do the first pass for repairs. We still need to get re-establish the permitted roadside campsites and run a grader down the road before opening. Likely to open by late November.
Cottonwood Canyon & Marble Canyon Roads - NPS road crew used a dozer to do the first pass for repairs. We still need to get re-establish the permited roadside campsites and run a grader down the road before opening. Likely to open by early November.
North Highway - this will open sometime after February 2024. Work will be done by the permanent repairs contract.(Access to: Fall Canyon Trail, Old Stovepipe Wells, Lower Titus Canyon, Ubehebe Crater, Racetrack Road)
Daylight Pass Road & Mud Canyon Road- contractors will start by making temporary repairs. The road will likely reopen by mid-November, but will have gravel sections and a lowered speed limit. Then a second contract will be awarded to do permanent pavement replacement, which may include adding protection from future floods. That contract is likely to start in February or March 2024.
Hole in the Wall Road - NPS road crew used a dozer to do the first pass for repairs. We still need to get re-establish the permitted roadside campsites and run a grader down the road before opening. Likely to open by late November.
Cottonwood Canyon & Marble Canyon Roads - NPS road crew used a dozer to do the first pass for repairs. We still need to get re-establish the permited roadside campsites and run a grader down the road before opening. Likely to open by early November.
North Highway - this will open sometime after February 2024. Work will be done by the permanent repairs contract.(Access to: Fall Canyon Trail, Old Stovepipe Wells, Lower Titus Canyon, Ubehebe Crater, Racetrack Road)
Daylight Pass Road & Mud Canyon Road- contractors will start by making temporary repairs. The road will likely reopen by mid-November, but will have gravel sections and a lowered speed limit. Then a second contract will be awarded to do permanent pavement replacement, which may include adding protection from future floods. That contract is likely to start in February or March 2024.